"Blue Bridge" Paint Job Running Ahead of Schedule in Owensboro

Emil Moffatt

The repainting of Owensboro's "Blue Bridge" is running ahead of schedule. Kentucky Transportation Cabinet spokesman Keith Todd says the original plan called for the bridge to be closed until late this year to allow painting to be completed on the main truss of the span, which connects Daviess County to southern Indiana.

"We think we'll be finished with the main truss around the middle of next week," Todd told WKU Public Radio Friday. "That will allow them to turn around and then begin painting the approach spans."

Todd says two full work crews have worked a combined twelve hours a day, seven days a week throughout the summer to get the main bulk of the work done on the span officially known as the Glover H. Cary bridge.

The contractor is hoping to have the approach spans painted before November 15th, when the bridge is set to re-open. An estimated 8,500 vehicles cross the Owensboro Blue Bridge daily.